EPC总包视角下海外石化项目防火涂料的综合评价与选型
Comprehensive evaluation and selection of fire protection coatings for overseas petrochemical projects from the perspective of EPC general contracting
浏览(5) 下载(0)
- DOI:
- 作者:
- 易亚男,戈敬姣,张乐琦,谷丰,骆惠
Yi Yanan, Ge Jingjiao, Zhang Leqi, Gu Feng, Luo Hui
- 作者单位:
- 1.中国石油工程建设有限公司,北京 100085; 2.中油国际管道有限公司,北京 102206; 3.佐敦涂料(张家港)有限公司,北京 100088
1. China Petroleum Engineering & Construction Corporation., Beijing 100085, China; 2. Sino-Pipeline International, Beijing 102206, China; 3. Jotun Coatings (Zhangjiagang) Co., Ltd., Beijing 100088, China
- 关键词:
- EPC总承包;模块化;撬装设备;防火涂料;水泥基非膨胀型;无溶剂环氧膨胀型;成本;现场管理
EPC general contracting; modularization; skid-mounted equipment; fire protection coating; cement-based intumescent; solvent-free epoxy intumescent; cost; on-site management
- 摘要:
- 随着EPC总承包海外石化项目撬装化、模块化建造模式的普及,钢结构防火涂料的国内工厂预制涂装
作业量占总涂装量的比例显著攀升。以EPC总包方视角,针对水泥基非膨胀型与无溶剂环氧膨胀型两类主流防
火涂料,结合中东区域项目实操经验,从成本造价、施工工期、现场HSE管控及质保维护4个维度开展定性与
定量对比研究。基于线性加权成本估算法构建成本测算模型,以10 000 m²涂装工程量为样本进行测算分析。
结果表明:当国内预制率大于 62%时,无溶剂环氧膨胀型防火涂料总成本即显现成本优势,且预制率越高成
本优势越显著;对材料价格±20%波动的敏感性分析进一步验证了该结论的稳健性。依据项目管理决策矩阵,
对于预制率不低于62%的海外石化项目,国内预制采用无溶剂环氧膨胀型防火涂料方案,可有效优化项目造
价、压缩工期,并可显著降低现场施工管控风险与质保期内运维成本。
As the skid-mounted and modular construction models in overseas petrochemical EPC projects are widely adopted,the proportion of fire protection coatings for steel structures applied in domestic shops are prefabrication now accounts for a significantly growing share of the total coating work. From the perspective of an EPC general contractor, this paper takes two mainstream fire protection coatings, namely cement-based non-intumescent coatings and solvent-free epoxy intumescent coatings, and combines practical experience of projects in the Middle East. On this basis, it carries out a combining qualitative and quantitative comparative study from four dimensions: the project cost, construction schedule, on-site HSE control, and warranty-period maintenance. A cost estimation model based on the linear weighted cost method is built, and a coating workload of 10 000 m² is employed as the calculation sample. The results show that when the domestic prefabrication rate is higher than 62% , solvent-free epoxy intumescent fire protection coatings demonstrate a cost advantage in terms of total cost. The higher prefabrication proportion leads to more pronounced cost advantages. Sensitivity analysis for±20% fluctuations in material prices also verifies the robustness of this conclusion. According to the project management decision matrix, for overseas petrochemical projects with a prefabrication rate no less than 62%, adopting domestically prefabricated solvent-free epoxy intumescent fire protection coatings can effectively optimize project cost, shorten the construction schedule, and significantly reduce on-site construction management risks as well as operation and maintenance costs during the warranty period.