33 kV变压器调试技术
Debugging Techniques of 33 kV Transformers
浏览(1677) 下载(2)
- DOI:
- 作者:
- 吴永亮, 杜照然
WU Yong-liang, DU Zhao-ran
- 作者单位:
- 中国石油天然气管道局管道投产运行公司, 河北廊坊065001
Commissioning and Operation Company of CPP, Langfang 065001, China
- 关键词:
- 变压器;调试;运行;绝缘;变压器油
transformer;debugging;operation;insulation;transformer oil
- 摘要:
- 通过对阿布扎比原油管道项目末站内33 kV变压器的调试,文章总结了该变压器投入运行前所需进行的测试项目,包括变压器油绝缘强度、绝缘电阻、直流电阻、变压比及接线组别、介质损耗因数、直流高压和交流耐压测试等,并简要说明了主要测试方法和步骤。
Based on the debugging of the 33 kV transformers at the terminal station of the Abu Dhabi crude oil pipeline, this article summarizes the main testing items before the transformers put into operation, including transformer oil dielectric strength, insulation resistance, DC resistance, voltage ratio and connection group, dielectric dissipation factor, DC and AC high voltage resistances. And the main testing methods and steps are briefly illustrated.2015,S1(S1): 57-59 收稿日期:2013-8-20DOI:10.3969/j.issn.1001-2206.2013.S1.016作者简介:吴永亮(1983-),男,黑方江齐齐哈尔人,助程师,2008年毕业于中北大学,现从事石油天然气行业电气仪表技术管理工作。