管道土建工程的冬季施工措施
Winter Construction Measures of Pipeline Civil Engineering
浏览(2057) 下载(5)
- DOI:
- 作者:
- 陈海雨, 曹刚, 李爱娟
CHEN Hai-yu, CAO Gang, LI Ai-juan
- 作者单位:
- 中油管道建设工程有限公司
China Petroleum Pipeline Construction Engineering Co.,Ltd.,Langfang 065000,China
- 关键词:
- 管道工程;土建工程;冬季施工
pipeline;civil engineering;winter construction
- 摘要:
- 在管道工程建设中,由于工期的需要有时不得不在冬季进行施工。当室外平均气温连续5 d稳定低于5℃时,应采取相应的冬季施工措施。文章结合大量的工程实践,主要从土建工程冬季施工的准备、冬季施工的主要技术质量控制、冬季施工中混凝土的常见质量通病和预防措施等方面进行了阐述。
For pipeline construction, sometimes winter construction has to be carried out because of time limit requirement. While the outdoor average temperature in five sequential days is steadily lower than 5℃,then winter construction measures should be taken. Based on a great deal of engineering practice, this paper describes winter construction preparation, key technical and quality control, common concrete defects and their prevention and cure measures.2009,S2(S2): 113-116 收稿日期:2009-8-1分类号:TE973作者简介:陈海雨(1977-),男,河北衡水人,工程师,2000 年毕业于大庆石油学院工业与民用建筑专业,现从事管道工程施工管理工作参考文献:
[1] 《建筑施工手册》编写组. 建筑施工手册(第四版)[M]. 北京:中国建筑工业出版社,2003.
[2] 李贵宾. 集输管道冬季施工措施[J]. 油气储运,2005,(10): 44-45.
[3] JGJ 104-1997, 建筑工程冬期施工规范[S].