X70钢管道冬季焊接和防腐的技术措施
Technical Measures for Winter Construction of X70 Steel Pipes
浏览(1857) 下载(4)
- DOI:
- 作者:
- 张存华, 张海力, 张明瑾, 张世梅
ZHANG Cun-hua, ZHANG Hai-li, ZHANG Ming-jin
- 作者单位:
- 中国石油天然气管道局
China Petroleum Pipeline Bureau,Langfang 065000,China
- 关键词:
- X70钢;焊接;保温;防腐;冬季施工
X70 steel;welding;thermal insulation;anticorrosion;winter construction
- 摘要:
- 在兰银管道工程建设中,通过认真研究和大量的实践,总结出了一套有效的X70钢管道冬季焊接和防腐的技术措施,包括焊前预热、焊接中防风保温、焊后和返修保温缓冷、补口作业的除湿和保温等,给今后管道工程高强钢管的冬季焊接和防腐施工提供了借鉴。
Through deepening research and large amounts of practical work, a set of technical measures of welding and anticorrosion for winter construction of Lan -Yin Pipeline are summarized including preheating before welding, wind -proof and heat preservation during welding, heat preservation and cooling delay after welding and during repair, dehumidifying and thermal insulation for field joint. This experience provides a reference for future winter welding and anticorrosion constructions of X70 high strength steel pipes.2009,S2(S2): 110-112 收稿日期:2009-8-1分类号:TE973.3作者简介:张存华(1972-),男,山东聊城人,工程师,1995 年毕业于承德石油高等专科学校焊接工艺及设备专业,现从事工程项目管理工作