EPC总承包工程的投产试运行管理
Commissioning Management of EPC General Contract Project
浏览(2050) 下载(3)
- DOI:
- 作者:
- 朱义明, 张晶, 田西宁, 邓勇
ZHU Yi-ming, ZHANG Jing, TIAN Xi-ning
- 作者单位:
- 中国石油天然气股份公司管道分公司长庆输油气分公司
PetroChina Changqing Oil Transportation Company,Yinchuan 750004,China
- 关键词:
- 管道工程;EPC总承包;试运投产;管理
pipeline engineering;EPC general contract;commissioning;management
- 摘要:
- 结合兰州—银川管道工程实践,论述了管道工程EPC总承包模式下试运投产的组织管理过程,由于试运投产工作参与单位较多,所以明确各自的职责、进行有效的协作非常重要。文章从组织协调、成立试运投产部、编制试运投产管理文件及方案和作业指导书、投产准备等方面介绍了管道工程试运投产的协调管理工作。
Based on the engineering practice of Lan-Yin Gas Transmission Pipeline Project, this paper discusses the organization and management of pipeline project commissioning under EPC general contract mode, stresses the importance of defining responsibility of each partners and conducting effective coordination among the partners. It describes the commissioning coordination management of the pipeline project from following aspects: organization coordination, establishment of commissioning department, compilation of commissioning management documents, schemes and operation guide books, and commissioning preparation work.2009,S2(S2): 41-43 收稿日期:2009-8-1分类号:F406.2作者简介:朱义明(1963-),男,江苏涟水人,工程师,1989 年毕业于中国石油管道学院自动化与仪表专业,现从事长输管道施工、试运、投产、维修管理工作参考文献: