兰银线EPC总承包模式下质量管理的探索
Exploring Quality Management of Lan -Yin Gas Transmission Pipeline under EPC General Contract Mode
浏览(1971) 下载(5)
- DOI:
- 作者:
- 吴兵1,2, 常宏2, 黄高优2
WU Bing1,2, CHANG Hong2, HUANG Gao-you2
- 作者单位:
- 1. 西安交通大学;
2. 长庆油田建设工程总公司
Changqing Oilfield Construction Engineering Co.,Xi'an 710000,China
- 关键词:
- 管道工程;EPC总承包;质量管理
pipeline engineering;EPC general contract;quality management
- 摘要:
- 结合兰银管道工程实践,对EPC总承包模式下的工程质量管理进行了探索,从分包商的选择、质量管理计划的编制、项目实施过程中质量管理的全过程控制,以及对各环节发生问题的分析总结和持续改进等方面,介绍了工程质量管理的具体做法。兰银线焊接一次合格率达到98%,整条线路投产一次成功,施工质量和进度管理取得了满意的效果。
Based on the engineering practice of Lan-Yin Gas Transmission Pipeline Project, the engineering quality management under EPC general contract mode was explored, and concrete methods of engineering quality management were adopted, such as selection of subcontractor, compilation of quality management plan, whole process control, analysis on problems in links and continuing improvements. The primary welding qualified rate of Lan-Yin Gas Transmission Pipeline reached 98%, the whole project was successfully put into production at one stroke, the construction quality and schedule management were satisfactory.2009,S2(S2): 26-29 收稿日期:2009-8-1分类号:F253.3作者简介:吴兵(1974-) ,男,陕西西安人,工程师,1998 年毕业于河北科技大学,2006 年毕业于西安石油大学,硕士,从事长输油气管道QHSE 管理工作参考文献: