1万 m3内浮顶油罐拱顶施工的一种新方法
A New Building Method for Arch Roof of 10000m3 Covered Floating Roof Oil Tank
浏览(1868) 下载(2)
- DOI:
- 作者:
- 刘佳恩
Liu Jiaen
- 作者单位:
- 中国石油天然气总公司第一建设公司
- 关键词:
- 储罐;施工
- 摘要:
- 石油-公司在武汉石油化工厂1万m3内浮顶油罐的施工中,总结了国内同行的经验,大胆尝试了水浮正装罐壁,然后在浮顶上设临时胎具,组装焊接拱顶的施工工艺。实践证明,该工艺施工方法简单,劳动强度低,安全可靠、施工质量容易保证,交叉作业容易,总的施工工期短。
In the construction of 10000m~3 covered floating roof oil tank in Wuhan Petro-chemical Plant, summing up other company's experiences, the First Construction Co. of COGC has made a bold innovation to install the tank walls upwards with water floating method and then set the tempora- ry die blocks on the floating roof for the arch roof assemblying and welding. The practise shows that such process has the advantages of easy installation, low labour force consumption. Safety and reliable, easy quality control and cross operation, and short total construction period.1989,2(2): 17-20,2,3 收稿日期:1988-8-27作者简介:作者生于1953年,1979年毕业于郑州工学院化学工程系化工机械专业.一直从事炼化装置及油、气储罐的施工安装工作,现任中国石油天然气总公司第一建设公司项目副经理。