用夺吊法分两段吊装反应再生器
To hoist and install reactive reprocessor in two sections using mast crane
浏览(1547) 下载(2)
- DOI:
- 作者:
- 廖长森
Liao Changsen
- 作者单位:
- 中油第六建设公司乙烯工程部,河南省濮阳市 457000
- 关键词:
- 石油化学工业;设备;吊装;施工
Petro-chenical industry;Equipment;Hoisting;Construction
- 摘要:
- 大型设备吊装的方法很多,在中原油田油气综合处理厂30万t/a催化裂化装置“两器”的吊装施工中,针对设备基础高、重量大的特点,考虑施工现场条件和吊装机具的限制,采用双桅杆夺吊法分两段进行吊装,获得成功。本文全面介绍了这种吊装方法。
During hoisting and installing a reactive reprocessor of the 300, 000t/a catalytic cracking equipment of the oil and gas treatment plant in Zhongyuan Oil Field, the reactive reprocessor was suceessfully hoisted and installed in two sections using a mast crane in order to counter the problems caused by the height of the equipment foundation and by the heaviness of the equipment.1995,5(5): 46-50 收稿日期:1995-3-27分类号:TE682