动臂桅杆分段吊装80m内衬隔热层钢烟囱
To Hoist a Steel Chimney of 80m in Height in Sections Using a Mast with Movable Arm
浏览(1758) 下载(1)
- DOI:
- 作者:
- 李力斌
Li Libin
- 作者单位:
- 中石化兰州炼油化工总厂安装公司, 甘肃省兰州市西固区 730060
- 关键词:
- 桅杆;吊装;设备;施工
- 摘要:
- 吊装直径较小的高耸烟囱具有一定难度,分段吊装可以减小其吊装吨位和吊装长度,化解不利因素。动臂桅杆的采用,减少了机具设备,扩大了桅杆作业范围,施工周期短,经济效益高。本文通过工程实例,介绍了动臂桅杆分段吊装80m钢烟囱的技术方案。
The lifting stress caused in welding long distance pipeline is detailedly analyzed and a formulafor calculating the lifing stress on any across section is derived. A typical program for calculation with computer is also compiled. The Lifting stress on commonly used steel pipes is analyzed with computer and a curve showing the relationship betwean the lifting stress and the lifting height is drawn out.1994,5(5): 17-19,2 收稿日期:1994-4-23分类号:TE682