高耸塔架桩基工程设计中的几个问题
Project design of pile foundation for high-erected towers
浏览(1767) 下载(2)
- DOI:
- 作者:
- 贾庆山
Jia Qingshan
- 作者单位:
- 高桥石化公司规划设计院 201208 上海市浦东新区
Shanghai
- 关键词:
- 塔;软地基;桩基础;沉降;承压能力;选择
Column;Soft ground;Pile foundation;Settling;Resistance to pressure;Selection
- 摘要:
- 在沿海软土地基上建立高耸塔架,对桩基的设计要求比较严格。本文结合某工程现场试桩资料进行分析研究,从选择桩尖持力层及进入持力层的深度、确定单桩极限承载力和控制桩基不均匀沉降等方面进行了探讨,并与十几年来30余座塔型构筑物桩基沉降数据的统计结果进行对比分析。
The technical requirements should be strictly met on the design of pile foundation for high towerson the offshore soft ground. Based on a project field testing result, this paper discusses the selection offormation of resistance to pressure and its depth to determine the maximum pile load to control the un-even subsidence of the pile foundation. It also presents the subsidence data collected from more than 30towers m recent years.1996,6(6): 7-10 收稿日期:1996-2-17参考文献:
1 JG194-94建筑桩基技术规范.
2 刘金砺.桩基础设计与计算.北京:中国建工出版社.1990.
3 胡人礼.桥梁桩基设计.北京:人民铁道出版社,1974.