西气东输管道工程概况
General Situation of Pipeline Construction in West China Gas Transported to East China Project.
浏览(1884) 下载(1)
- DOI:
- 作者:
- 褚永杰
Chu Yongjie
- 作者单位:
- 中油气管道局西气东输办公室
Langfang,Hebei
- 关键词:
- 天然气管道;工程;总体设计;方案;概况
natural gas pipeline;engineering;overall desigh;project
- 摘要:
- 西气东输是西部大开发的标志性工程,而其管道工程又是西气东输的主体工程。文章概述了西气东输管道工程的特点、建设水平、工程标段划分及工期安排,并着重从管道用材、线路分布、内涂层、外防腐、穿跨越、站场、道路、检测、监理等方面介绍了工程量和实施方案,展示了西气东输管道工程的总体框架。
West China gas transported to east China is a mark project for west China's great development and pipeline construction is a main project in west China gas transported to east China project. The paper generally introduced the pipeline project's characteristic,construction level,construction stage & schedule and emphatically introduced the project quantity & implementation program from many aspects such as pipeline material, route distribution, internal coating, external anti-corrosion, pipeline crossing & aerial crossing, testing & supervision etc.and showed the general frame of west China gas transported to east China pipeline project.2001,4(4): 1-2 收稿日期:2001-5-30分类号:F426.2作者简介:褚永杰,高级工程师。年毕业于中国人民大学基本建设经济专业,历任中国石油天然气管道局第四工程公司经理、电力通信工程公司经理,现任中国石油天然气管道局西气东输工程建设领导小组办公室主任。