国际工程总承包项目的后期管理
Final Management of International Contract Project
浏览(1697) 下载(1)
- DOI:
- 作者:
- 刘亚利
Liu Yali
- 作者单位:
- 中国石油工程建设(集团)公司
- 关键词:
- 国际工程;后期管理;经验;探讨
international project;final management;experience;discussion
- 摘要:
- 作者以参加科威特集油站项目,尤其是该项目后期管理的切身体验,分析了该项目收尾工作进展艰难的原因,即业主和承包商对合同某些条款的认识不一致以及由业主负责试运和性能测试是影响收尾工作和项目交工最主要的因素。总结了对国际工程总承包项目后期管理的认识,同时介绍了项目后期管理的工作内容及概况。
With the experience of taking part in Kuwait oil gathering center project, especially with the experience of this project final management, the writer analyzes the cause of this project final work difficult, i.e. owner contractor have different views for some contract items and owner is charge for preliminary operation performance test, these two aspects are main facts to influence this project final working hand-over. Last, the paper summarizes the know ledges for international contract project final management introduces the working contents general situation the project final management.2002,6(6): 44-46,4 收稿日期:2002-9-6分类号:F426作者简介:刘亚利,1968年毕业于北京石油学院储运专业.历任中石油第六建设公司施工管理科长、副经理、总经济师,北京集输公司处长、总经理助理.中国石油工程(集团)公司总经理助理.现任科威特集油站项目负责人.自1996年该项目开始,参加了项目的设计、采办、施工、交工、试运、性能测试等全过程的工作.目前负责该项目两站一线的试运和性能测试以及收尾阶段的各项工作.参考文献:
[1]汤礼智.国际工程承包总论.北京:中国建筑出版社,1997
[2]梁金监.国际工程施工索赔.北京:中国建筑出版社,1996
[3]科威特西部油田设施扩建-27、28号集油站和传输管线项目合同