大型固定式平台整体化建造技术
Construction Technology for Large Scale Fixed Platform in Integration
浏览(1678) 下载(2)
- DOI:
- 作者:
- 臧全斋
ZANG Quan-zhai
- 作者单位:
- 胜利油田胜利石油化工建设有限责任公司
- 关键词:
- 大型平台;整体化;预制;打桩;装船;运输;就位安装
large scale platform;integration;prefabricated;piling;shipment transportation;installation
- 摘要:
- 赵东区块初期开发工程主要包括ODA钻井平台和OPA生产平台,其中ODA是目前国内建造的最大最重的平台,平台桩基不设导管架,施工难度大.本文根据项目特点,以ODA为例着重介绍了大型固定式海上平台的陆上整体预制、称重、滑移装船、海上运输、海上打桩和整体海上就位施工方案、方法、设施、程序和要求,并阐述了海上运输的应急措施和就位安装注意事顶.实践证明,运用该整体化建造技术建造海上大型平台,可缩短海上安装时间,减少海上气候的影响,降低施工风险.不仅适应于浅海平台制造,更适合深海水域大型平台建造.
Zhaodong piece development projects of initial stage include the ODA platform of well drilling and OPA production platform mainly,in which,ODA is the biggest most heavy platform of present domestic platforms,it's stake base does not set up conduit to put up, construction difficulty is big.According to project characteristic,taking ODA for example,overall aspects have been introduced such as prefabrication on land,weight,slip shipment,marine transportation,piling and installation of large scale marine platform including overall program of construction,method,facility and notice items for installation program and requirements.The emergency measures of marine transportation are also included.2003,2(2): 13-17 收稿日期:2003-1-17分类号:TE54作者简介:减全斋,高级工程师.1985年毕业于华东石油学院机械系储运专业,现任胜利石油化工建设有限责任公司总工程师.一直从事工程技术质量管理工作,先后参加了孤东1号、2号联合站、科威特集油站、绥中36-1陆上终端和赵东区块初期开发ODA, OPA平台等大型工程的施工管理工作.