西气东输二线西段阀室施工质量控制
Valve Chamber Construction Management in Second West to East Gas Pipeline Project
浏览(1620) 下载(4)
- DOI:
- 作者:
- 李婷, 于航, 胡超
LI Ting, YU Hang, HU Chao
- 作者单位:
- 大庆油田建设集团有限责任公司
Daqing Oilfield Construction Group Co., Ltd., Daqing 163712, China
- 关键词:
- 长输管道;阀室;施工方法
long-distance pipeline;valve chamber;construction method
- 摘要:
- 通过西气东输二线西段管道工程建设,对阀室施工和主体管道施工之间的先后顺序、标高、方位控制、阀门安装、整体试压等重要工序进行了详细阐述,提出了先主体管道下沟,后截断阀室段管道、控制标高、精确定位的施工工序,较好地将工艺管道安装和土建施工衔接起来,经第9A标段的施工证明,该施工方法达到了节省施工资源、提高施工质量的预期目的。
Associated with the construction of West Section of Second West to East Gas Pipeline Project,the main construction procedures such as the construction sequences between valve chamber and main pipeline, elevation and orientation control, valve installation and integral pressure test were illustrated. The working procedure was made out, that was "lowering main pipeline into trench, then cutting the pipeline section located in valve chamber, controlling elevation and making accurate positioning". The working procedure linked up the process pipeline installation and the civil construction closely. This construction method used in the 9A bidding section has proved that it achieved the goal of saving construction resources and raising construction quality.2010,S1(S1): 269-272 收稿日期:2010-9-2分类号:TE973作者简介:李婷(1983-),女,陕西岐山人,助理工程师,2007年毕业于西安石油大学石油工程学院油气储运工程专业,从事输气管道工程以及能源管理和计划统计工作参考文献:
[1] Q/SY GJX0120-2008,西气东输二线管道工程站场安装技术规范[S].
[2] SY 4203-2007,石油天然气建设工程施工质量验收规范站内工艺管道工程S].
[3] SY 4200-2007,石油天然气建设工程施工质量验收规范通则[S].