西气东输二线西段X80钢管道冬季焊接施工措施
Measures for X80 Steel Construction in Winter in West Section of Second West to East Gas Pipeline Project
浏览(1703) 下载(4)
- DOI:
- 作者:
- 潘会彬, 王建国, 杨明新
PAN Hui-bin, WANG Jian-guo, Yang Ming-xin
- 作者单位:
- 中国石油天然气管道局国内事业部
Domestic Department of China Petroleum Pipeline Bureau, Langfang 065000, China
- 关键词:
- 西气东输二线;X80钢管道;冬季施工;措施
Second West to East Gas Pipeline Project;X80 steel;construction in winter;measure
- 摘要:
- 西气东输二线西段工程从2008年11月份至2009年3月份,全线进入冬季施工。通过采取一系列技术、质量、管理措施,EPC项目部按期保质保量完成了冬季施工任务,并取得了优异的成绩。文章结合工程实际,从EPC角度出发,对西气东输二线西段冬季施工中所采取的这些措施进行了总结和阐述。
The construction of the whole West Section of Second West to East Gas Pipeline was fulfilled in winter from Sept. 2008 to March 2009. By means of a series of measures with respect to technology, quality and management, the EPC Project Department of West Section of Second West to East Gas Pipeline Project finished the winter construction work in good quality and quantity and on schedule. The measures taken in winter construction of the project were summarized in combination with the engineering practice and in view of EPC general contract.2010,S1(S1): 251-253 收稿日期:2010-9-27分类号:TE973作者简介:潘会彬(1975-),男,山西寿阳人,工程师,一级注册建造师,监理工程师,2008年毕业于天津大学管理学院,工程硕士,主要从事管道工程的施工管理、质量管理工作参考文献: