管道通过地震断裂带施工技术
Pipeline Construction Technology Applied in Seismic Fault Zone
浏览(1801) 下载(1)
- DOI:
- 作者:
- 高云宇, 王丽, 张涛
GAO Yun-yu, WANG Li, ZHANG Tao
- 作者单位:
- 中国石油天然气管道局河北华北石油工程建设有限公司
Hebei Huabei Petroleum Engineering Construction Co., Ltd. of China Petroleum Pipeline Bureau, Renqiu 062552, China
- 关键词:
- 管道工程;地震断裂带;施工;技术总结
pipeline engineering;seismic fault zone;construction;technical summary
- 摘要:
- 西气东输二线管道工程西段第1、2A标段线路工程通过了两条地震断裂带,即喀什河断裂带和博阿断裂带,针对这两条断裂带的管道施工,从管材要求、防腐要求、环焊缝性能要求、管道抗震措施、管道抗震施工、管道线路工程抗震验收等方面进行了施工技术总结,可供类似工程借鉴。
The first and the 2A bidding sections of West Section of Second West to East Gas Pipeline Project pass through two seismic fault zones, i.e. Keshi River seismic fault zone and Boa seismic fault zone.The technical summary on the pipeline construction in these two seismic fault zones is presented in aspects of pipe material, anticorrosion and girth welding performance as well as pipeline aseismic measures, aseismic construction and engineering aseismic check before acceptance, which will provide useful experience for similar projects.2010,S1(S1): 221-223 收稿日期:2010-10-18分类号:TE973.1作者简介:高云宇(1975-),男,河北丰宁人,高级工程师,1996年毕业于河北工业大学化工设备与机械专业,从事石油天然气管道技术管理工作。参考文献:
[1] QSY GJX 0109-2008,西气东输二线管道工程线路工程施工技术规范[S]