多预埋地脚螺栓设备安装方法探讨
Installation Method of Multi Pre-embedded Foundation Bolts of Equipment
浏览(2215) 下载(5)
- DOI:
- 作者:
- 杨永霞, 王旭兰, 张新忠
YANG Yong-xia
- 作者单位:
- 长庆油田分公司建设工程处 陕西西安 710086
Construction Engineering Division of Changqing Oilfield Company, Changqing 710086, China
- 关键词:
- 地脚螺栓;定位盘;位置精度;安装方法
foundation bolt;positioning pan;position precision;installation method
- 摘要:
- 对于原油稳定塔、小型的烟囱和火炬塔等类似设备,混凝土基础的体积较小,但预埋地脚螺栓的数量较多,从基础施工完成后设备的吊装就位来说,预埋地脚螺栓的相对位置精度是保证设备一次吊装就位成功的关键。文章针对该类设备的安装方法进行探讨,通过制作地脚螺栓定位盘并组焊成地脚螺栓构件的方法来控制位置精度,从而保证了设备的一次吊装就位成功。
For the equipment such as crude oil stabilizer,small-scale chimney and flare stack,the volume of concrete foundation is not large,but the number of pre-embedded foundation bolts is big.The relative position precision of the pre-embedded foundation bolts is the key to successfully hoist and position the equipment in one time.In this paper,the installation method for such kinds of equipment is discussed and an effective approach to control installation precision is illustrated in detail,which is to make a foundation bolt positioning pan and weld it into a foundation bolt structure.The practical usage of the foundation bolt structure in the equipment installation is successful.2013,4(4): 48-50 收稿日期:2014-4-28DOI:10.3969/j.issn.1001-2206.2013.04.014作者简介:杨永霞(1984-),女,甘肃永登人,助理工程师,2007年毕业于中国石油大学(华东)机电工程学院,主要从事油气田地面产建工程技术管理工作。