软硬交错地层中的定向钻穿越施工技术
Directional Drilling Crossing Construction Technique Used in Interleaved Strata of Soft Clay and Hard Rock
浏览(2430) 下载(7)
- DOI:
- 作者:
- 王海, 楼岱莹, 屠言辉
WANG Hai
- 作者单位:
- 中国石油天然气管道局穿越分公司 河北廊坊 065001
China Petroleum Pipeline Bureau Crossing Company, Langfang 065001, China
- 关键词:
- 水平定向钻;软硬交错地层;扩孔台阶
HDD;interleaved strata of soft clay and hard rock;step shaped in reaming process
- 摘要:
- 随着西气东输二线管道工程的建设,水平定向钻穿越施工的管道管径也随之增大。在大口径水平定向钻穿越施工中,软硬地层交错处产生的扩孔台阶是影响定向钻施工成功率的关键因素。文章通过理论分析,采用了一种使扩孔器承受的垂直向下合力减小的施工方案,从而有效地避免了在软硬地层交错处产生扩孔台阶。工程实践证明该方法可行。
With the construction of the Second West to East Gas Transmission Pipeline, the diameter of pipeline constructed by HDD technique becomes bigger. In HDD construction of large diameter pipeline, step shaped in interleaved strata of soft clay and hard rock during reaming process is a fatal factor that affects construction success rate. This paper gives a method to reduce or avoid the step shaped in reaming process through theoretical analysis, which enables the downward resultant force on the reamer to decrease. The engineering practice proves that method is feasible.2013,4(4): 41-44 收稿日期:2012-4-13DOI:10.3969/j.issn.1001-2206.2013.04.011作者简介:王海(1963-),男,天津人,高级工程师,1983年毕业于太原重型机械学院工程机械专业,2003年起从事水平定向钻穿越施工技术管理工作。参考文献: