富拉电厂输气管道EPCC项目采办实务与探索
Procurement Practice and Exploration of EPCC Project for Gas Pipeline at Fula Power Plant in Sudan
浏览(2401) 下载(2)
- DOI:
- 作者:
- 王国强, 蒋金海, 赵寅
WANG Guoqiang
- 作者单位:
- 中原石油勘探局工程建设总公司
Engineering Construction General Company of Zhongyuan Petroleum Exploration Bureau, SINOPEC, Puyang 457001, China
- 关键词:
- 国际项目;采办流程;采办实务;进度控制;风险控制
international project;procurement process;procurement practice;schedule control;risk control
- 摘要:
- 在EPCC项目中,由于诸多因素影响,采办进度滞后、交货延迟的现象时有发生,进而导致项目延期。文章对项目具体情况、采办流程、采办务实及其案例进行分析,总结了采办管理的一些经验,展望了采办发展趋势,以期为同行提供借鉴。
In EPCC projects, lagged procurement and delayed consignment often occur because of many influence factors, which will lead to postpone the project completion. This paper describes the procurement process, procurement practice and case study, summarizes some experience about procurement management, and looks forward to the development trend of procurement management.2013,2(2): 77-80 收稿日期:2012-1-16DOI:10.3969/j.issn.1001-2206.2013.02.024分类号:F416.61;F426.22作者简介:王国强(1967-),男,河南林县人,1988 年毕业于承德石油高等技术专科学校焊接设备与工艺专业,现从事石油工程建设施工技术及采办管理工作。参考文献:
[1] 美国项目管理协会. 项目管理知识体系指南(PMBOK 指南)[M].王勇, 张斌,译. 北京:电子工业出版社,2011.
[2] 张水波, 陈勇强. 国际工程总承包EPC 交钥匙合同与管理[M]. 北 京:中国电力出版社,2009.
[3] 李艳成. 采购管理的新趋势[J]. 中国物流与采购,2003,(11): 58-59.
[4] 中国石油天然气管道局中亚地区工程项目部. 中亚天然气管道 工程项目管理与技术文集[C]. 北京:石油工业出版社, 2010.182- 209.
[5] 徐海波,王建顺,王双喜. 对EPC 模式下采办工作的重新认识[J]. 石油工程建设,2010,36(增刊):142-145.