不平衡报价法在国际工程商务报价中的研究与应用
Research and Application of Unbalanced Pricing Method in Commercial Quotation for International Projects
浏览(2331) 下载(3)
- DOI:
- 作者:
- 陈志勇
CHEN Zhi-yong
- 作者单位:
- 中国石油工程建设公司, 北京 100120
China Petroleum Engineering and Construction Corp., Beijing 100120
- 关键词:
- 不平衡报价;工程量清单;风险管理
unbalanced pricing;bill of quantity;risk management
- 摘要:
- 从承包商的角度出发探讨了不平衡报价的原理,提出了不平衡报价的计算模型,对不平衡报价的风险进行了分析讨论。通过某国油田地面建设项目实践案例,阐述了不平衡报价模型对提高项目经济效益的现实意义。
The Paper, from the perspective of an EPC contractor, studies unbalanced pricing method, puts forward the calculation model of unbalanced pricing method and discusses risk management for the method. On the basis of a case study for an international oilfield surface facilities project, the author expounds that application of unbalanced pricing model in bidding stage shows an important significance of improving economic benefits in project settlement2011,5(5): 56-59 收稿日期:2011-2-11分类号:F284作者简介:陈志勇(1963-),男,江苏泰兴人,工程师,1987年毕业于江苏广播电视大学工业与民用建筑专业,现从事工程项目投标报价、项目风险管理及项目成本控制工作.参考文献:
[1]张东华.浅谈工程建设投标报价策略与技巧[J].工程经济,2004,(9):33-35.
[2]白明,刘志伟.合同条件下不平衡报价的规划模型[J].辽宁石油化工大学学报,2002,26(4):82-85.
[3]卢有杰.不平衡报价的风险估测[J].建筑经济,1996,(3):17-18.
[4]黄新忠.试论不平衡报价的防范与控制[J].建筑经济,2009,320(6):61-64.