阿尔及利亚长距离输水管道水力分析及优化
Hydraulic Analysis and Optimization of Long-distance Water Supply Pipeline in Algeria
浏览(2421) 下载(1)
- DOI:
- 作者:
- 程鲁丰, 张涛, 罗双全, 尹兴奕
CHENG Lu-feng
- 作者单位:
- 中国石油工程建设公司, 北京 100120
China Petroleum Engineering and Construction Corp.,Beijing 100120
- 关键词:
- 长距离输水管道;水力分析;设计;优化
long-distance water supply pipeline;hydraulic analysis;design;optimization
- 摘要:
- 针对阿尔及利亚因萨拉赫到塔曼拉撒特长距离输水管道项目初步设计中水力设计存在的问题,开展了全程静态水力分析,指出了原初步设计中水力计算存在的问题和不足,采用改变部分泵站蓄水池高程和输水泵叶轮的方案优化了全程水力计算,解决了原初步设计中水力设计的问题,避免了需重新布局泵站或更换引擎可能造成的重大经济损失。
To resolve the problems existing in the preliminary design of the long-distance potable water supply pipeline from Salah to Tamanrasset in Algeria,static hydraulic analysis for the whole pipeline is carried out.The scheme of altering elevations of reservoirs and pump impellers at partial pump stations optimizes the hydraulic calculation for the whole pipeline and resolves the original problems.It avoids possible economic loss caused by relocating pump stations or altering engines.2011,3(3): 47-50 收稿日期:2011-1-20分类号:TE4作者简介:程鲁丰(1963-),男,山东菏泽人,高级工程师,1984年毕业于中国石油大学,主要从事国外EPC石油工程项目管理等方面工作.参考文献:
[1] 李家星.水力学[M] .南京:河海大学出版社,2001.127-128.
[2] GB 50013-2006,室外给水设计规范[S].
[3] 陈乃祥.离心泵[M] .北京:机械工业出版社,2003.68-71.