兰州—银川输气管道工程冬季施工措施
Measures for Winter Construction of Lanzhou-Yinchuan Gas Pipeline Project
浏览(3549) 下载(3)
- DOI:
- 作者:
- 吴兵1, 黄高优2, 赵文轸1
WU Bing1, HUANG Gao-you2, ZHAO Wen-zhen1
- 作者单位:
- 1.西安交通大学材料工程学院, 陕西西安 710049;
2.长庆建设工程总公司, 陕西西安 710038
Material Engineering Collage of Xi'an Jiaotong University, Xi'an 710049
- 关键词:
- 输气管道;冬季施工;质量保证措施
gas transmission pipeline;construction in winter;quality ensurence measure
- 摘要:
- 兰州—银川输气管道工程五单元位于贺兰山的垭口和银川的平吉堡之间,共12.84km,在冬季进行施工,由于气温低,风大,施工中遇到的主要问题都是由温度低造成的,为确保冬季施工质量,在焊接、防腐保温和设备管理方面采取了一系列相应的措施,包括:焊前预热、层间电加热带保温、焊后用石棉保温被保温、设置防风棚、用帆布包扎管口、缩短包裹收缩带前的准备时间、烘烤底漆、碾压等,成功地避免了冷裂纹的出现,保证了施工质量。最后对相关问题进行了讨论。
The fifth section of Lanzhou-Yinchuan Gas Pipeline Project is located between Yakou of Helanshan and Pingjibao of Yinchuan and is 12.84 km long. Main difficulties encountered during winter construction are caused by low temperatures and strong winds. In order to guarantee the winter construction quality, a series of countermeasures of welding, anticorrosion and thermal insulation as well as equipment management were taken, which include preheating prior to welding, applying interlayer heating belts for thermal insulation and asbestos quilt for thermal maintenance after welding, erecting windproof shed, binding up pipe ends with canvas, shortening preparation time of shrinkage belt enwrapping, primer baking and rolling. They avoided successfully the occurrence of cold cracks and ensured the construction quality. At last, some problems related to winter construction are discussed in this paper.2007,05(05): 78-80 收稿日期:2007-3-28分类号:TE973.9作者简介:吴兵(1974-), 男, 陕西人, 工程师, 毕业于西安石油大学油气储运专业, 硕士, 参加过长输油气管道安全管理地理信息系统的开发等科研项目, 现为西安交通大学材料工程学院在读博士研究生.