福建东西溪硬岩定向钻穿越施工
Pipeline Crossing Construction with Directional Drilling in Hard Rock Area of Dongxixi, Fujian
浏览(2231) 下载(4)
- DOI:
- 作者:
- 楼岱莹, 尹刚乾
LOU Dai-ying
- 作者单位:
- 中国石油天然气管道局穿越公司,河北廊坊 065001
China Petroleum Pipeline Bureau Crossing Company,Langfang 065001,China
- 关键词:
- 长输管道;定向钻穿越;硬岩;施工技术
long-distance transmission pipeline;crossing with directional drilling;hard rock;construction technology
- 摘要:
- 福建东西溪硬岩定向钻穿越施工,遇到的主要难题是入土点侧和出土点侧卵石层深约14~17m,穿越的大部分地层为花岗岩,长度约1500m。为此,在该穿越施工中采用了三项关键技术:超长距离夯套管技术、硬岩导向孔对接技术、硬岩扩孔技术。文章简要介绍了该穿越施工的过程及三项关键技术的应用情况。福建东西溪硬岩定向钻穿越成功,创造了国内硬岩定向钻穿越的最长纪录(1690m)。
In the pipeline crossing construction with directional drilling in Dongxixi,Fujian,the major challenge encountered is the thick pebble layer of 14~17 m on the both entering side and exiting side.The main stratum in the pipeline crossing area consists of granite with the length of 1 500 m.Therefore,three key techniques are adopted in this crossing construction,i.e.ramming casing in ultra long distance,pilot hole interconnecting in hard rock and reaming hole in hard rock.The crossing construction course and application of these key techniques are illustrated in this paper.This successful crossing project has created a domestic record of the longest distance crossing with directional drilling in hard rock.2009,4(4): 32-33 收稿日期:2008-9-1分类号:TE973.4作者简介:楼岱莹(1980- ),男,浙江永康人,2004年毕业于中国石油大学(华东),硕士研究生,从事水平定向钻穿越施工技术工作.?